Secured unanimous three arbitrator defense award on behalf of multi-state engineering firm on a $12 Million Claim for the design and rehabilitation of a wastewater treatment facility.
During these challenging times, Severson & Werson remains open and in full operation, consistent with the firm’s previously established contingency planning. While many of our attorneys and staff will be working remotely, as a firm, we continue in full operation. We are here to help, as always.
Secured unanimous three arbitrator defense award on behalf of multi-state engineering firm on a $12 Million Claim for the design and rehabilitation of a wastewater treatment facility.