Severson & Werson
 
 
 

Construction Practice Group - Case Law Alert:

Professional Engineer Found to Have No Duty to Property Owner or Contractor

 

By David A. Ericksen

December 27, 2004

 

The California Court of Appeal last week confirmed a holiday gift to one very fortunate California engineer.  In Weseloh Family Limited Partnership v. K.L. Wessel Construction Co., Inc., et al. , 2004 DJDAR 15150, an engineer escaped a $6 million property damage claim on the grounds that it did not owe either the owner or general contractor a duty of care.  The Court's rationale for this "free pass" provides design professionals with a guide that is both instructive and cautionary.

The underlying facts of the case are relatively simple.  The project involved the design and construction of a large Southern California auto dealership, including the retaining walls that stood adjacent to the dealership.  The property owner hired a general contractor to construct the dealership facility, and the general contractor hired a specialty retaining wall subcontractor to construct two Keystone retaining walls.  In turn, the subcontractor retained an engineer to design the walls.  While the engineer did no construction work, it did provide design services and calculations that it signed and stamped on the subcontractor's behalf.  It also inspected and approved the completed walls.

Ultimately, a portion of the retaining walls failed, causing severe damage to the dealership.  The failure was allegedly caused by the engineer's erroneous calculations.  As a result, both the property owner and the general contractor sued the engineer for professional negligence and other claims.  Following an extensive analysis, the Court found that the engineer did not owe a duty of care to either the property owner or general contractor, and dismissed all of the claims.  The Court noted that the engineer's contract was solely with the subcontractor and not with the owner or general contractor, and neither the contract nor the services manifested an intention to benefit either the property owner or the general contractor.  The Court made this finding even though the design was expected to be implemented on the property owner's land and was a part of the general contractor's contractual obligations.

The Court's discussion identifies many possible loopholes for future claimants, but it also makes clear that professional service agreements, and how they are performed, can make a true difference.  The difference for the lucky engineer here may have been as much as $6 million.  Some of the key lessons for design professionals from the Weseloh decision are as follows:

*          Statements of intended beneficiaries in the design professionals' contracts and work product make a difference.  Their breadth should be as limited as possible.  Such clauses are standard in many design professionals' service agreements.  We have had little trouble negotiating them into our clients' agreements.

*          The purpose and recipients of construction observation reports should be clearly documented and their distribution should be limited.  The Court found that the engineer's observations in this case were intended solely for the benefit of the subcontractor in order to confirm that it had completed its work and they were not intended to provide a similar assurance to the owner or general contractor.

*          Indemnity provisions are also critical.  Prime consultants should make certain that they receive appropriate indemnity obligations from all subconsultants and, if applicable, from sub - subconsultants.  Absent such indemnity agreements, prime consultants might have no recourse against the sub-subconsultants.  Similarly, subconsultants should limit their indemnity obligations to their direct clients.  Had the engineer in Weseloh included the owner or general contractor as indemnitees or as additional insureds, the outcome of the case would have been very different.

*          Documenting construction deviations from the design drawings is critical.  The mere possibility that such deviations existed here was enough to break the causal chain from the errant calculation to the failure of the wall.

The clear message of the case is that under the right circumstances and with the appropriate contractual preparation and performance, a design professional may limit its liability exposure to a very small group.  While liability turns on a complex analysis of the relationship between the parties and the professional services provided, it is a message of hope and encouragement to those who take risk management seriously.

If you have any questions about this decision or its impact on your contracts or practice, or if you would like to discuss other risk management issues that are relevant to your practice, please contact David Ericksen    (   (415) 677-5637 or dae@severson.com   ) or any of Severson & Werson's fifteen construction attorneys   who   can all be reached by telephone at (415) 398-3344 or through the firm's website at www.severson.com. 

 
 
 
 

Copyright 2008, Severson & Werson, a professional corporation